🏗️ Belgium: Google halts construction of its data centre near Charleroi on authorities' order

· 3 min

Solar field at Google's data centre campus in Saint-Ghislain, Belgium

In brief


🏗️ Google has halted work on its data centre project at Farciennes near Charleroi. A spokesperson confirmed to AFP on Saturday that the company had stopped work in line with the direction of local authorities and was awaiting further guidance, adding that Google has operated in Belgium for more than 15 years and remains committed to complying with local laws. ⚖️ On Friday the authorities of the Wallonia region told the company to stop work on the 50-hectare former mining site because it did not have planning permission. Their spokesman Nicolas Yernaux called it a major offence: the illegal construction of a building covering three hectares. 💧 Behind the halt is a months-long dispute over water. Google applied to change its permit so the facility could be cooled with water drawn from the nearby River Sambre, rather than with air as first planned. After a dry season, the region refused over the summer. Google has challenged that decision, and according to AFP a hearing is scheduled for January.


📜 How the dispute began. The original permit for the site on the Sambre dates from 2024 and assumed air cooling. Google later asked for a change: according to the Belgian agency Belga, the company wants to merge two planned data centres on the site into one and cool the servers with river water. The amended permit was granted at first. A resident appealed, however, and in August Wallonia's minister for planning and infrastructure, François Desquesnes, refused the change.

💧 The numbers behind the refusal. According to the minister, the request covered drawing 600 cubic metres of water an hour, of which less than a quarter would be returned to the river. Desquesnes cited the strained state of Wallonia's water resources and the prospect of more and more droughts in the years ahead. Persistent dry weather in the region since spring had sharpened fears about tapping the Sambre and fuelled local opposition.

🏛️ The legal route. At the end of October Google confirmed it had appealed the minister's decision to Belgium's Council of State, the country's highest administrative court. A spokesperson said then, according to Belga, that the company is committed to using water and electricity responsibly and efficiently and wants to continue its dialogue with the authorities. The region now appears to treat the ongoing work as construction without a valid basis, which is why it ordered the stop. Neither Google nor the authorities have publicly detailed which parts of the build are affected.

🌍 A European pattern. Belgium is not alone: big tech companies are building data centres across Europe to support the artificial intelligence boom, and water, power and land are becoming points of conflict. In Belgium, Google has run a large data centre campus at Saint-Ghislain near Mons for years; Farciennes was meant to be its second site in Wallonia.

🔎 What is open. As far as is known, the site stays idle until the January hearing. Whether Google can then carry on with air cooling, push through its water plans or faces further delay depends on the courts and on further guidance from the region.